Planning time: the critical path
Give each piece of work an estimate in working days. Then ask, for every task: what must be finished before this one can start? You cannot clean data you have not collected.
- Dependency
- A link between tasks: one cannot start (or finish) until another has. The most common is finish-to-start. Saved to your glossary